In an agile and adaptive project, which scope management entity involves stakeholder engagement?

The correct answer is A. Collect Requirements. In agile and adaptive environments, Collect Requirements is the process most heavily driven by continuous stakeholder engagement. Requirements are gathered iteratively through user stories, backlog refinement, sprint reviews, and direct collaboration with stakeholders and…

Agile Frameworks/Methodologies

Question

In an agile and adaptive project, which scope management entity involves stakeholder engagement?

Options

  • ACollect Requirements
  • BCreate work breakdown structure (WBS)
  • CPlan Scope Management
  • DScope Baseline

How the community answered

(29 responses)
  • A
    93% (27)
  • B
    3% (1)
  • C
    3% (1)

Explanation

In agile and adaptive environments, Collect Requirements is the process most heavily driven by continuous stakeholder engagement. Requirements are gathered iteratively through user stories, backlog refinement, sprint reviews, and direct collaboration with stakeholders and customers. Agile emphasizes ongoing stakeholder involvement to refine and reprioritize the product backlog. Create WBS (B) is a decomposition activity done by the team. Plan Scope Management (C) is a planning process typically led by the project manager. The Scope Baseline (D) is a document/output, not a process involving stakeholder engagement.

Topics

#Scope Management#Stakeholder Engagement#Requirements Gathering#Agile Principles