CAPM · Question #251
CAPM Question #251: Real Exam Question with Answer & Explanation
The correct answer is B: Plan Quality Management. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables. Which process is the project manager executing?
Options
- AManage Quality
- BPlan Quality Management
- CControl Quality
- DPlan Scope Management
Topics
#Quality Management#Plan Quality Management#Project Planning#Quality Metrics