CAPM · Question #251
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the qualit
The correct answer is B. Plan Quality Management. Plan Quality Management is the process of identifying quality requirements and standards for the project and its deliverables, and documenting how the project will demonstrate compliance. Defining quality objectives, tools to be used, and quality metrics are all planning activiti
Question
Options
- AManage Quality
- BPlan Quality Management
- CControl Quality
- DPlan Scope Management
How the community answered
(34 responses)- A18% (6)
- B71% (24)
- C9% (3)
- D3% (1)
Explanation
Plan Quality Management is the process of identifying quality requirements and standards for the project and its deliverables, and documenting how the project will demonstrate compliance. Defining quality objectives, tools to be used, and quality metrics are all planning activities. Manage Quality (A) involves auditing quality requirements and using quality tools during execution. Control Quality (C) involves monitoring and recording results of quality activities. Plan Scope Management (D) is about defining how scope will be managed, not quality.