A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables. Which process is the project manager executing?

Options

  • AManage Quality
  • BPlan Quality Management
  • CControl Quality
  • DPlan Scope Management

Topics

#Quality Management#Plan Quality Management#Project Planning#Quality Metrics