Which statement summarizes the role of the change control board?
Sign in or unlock CAPM to reveal the answer and full explanation for question #25. The question stem and answer options stay visible for context.
Predictive, Plan-Based Methodologies
Question
Which statement summarizes the role of the change control board?
Options
- AThe change control board is responsible for presenting the change for approval
- BThe change control board will analyze the change impact in terms of cost and schedule
- CThe change control board is responsible for managing the change management and configuration management systems
- DThe change control board is responsible for reviewing and approving changes to the project
Unlock CAPM to see the answer