CAPM · Question #25
CAPM Question #25: Real Exam Question with Answer & Explanation
The correct answer is D: The change control board is responsible for reviewing and approving changes to the project. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which statement summarizes the role of the change control board?
Options
- AThe change control board is responsible for presenting the change for approval
- BThe change control board will analyze the change impact in terms of cost and schedule
- CThe change control board is responsible for managing the change management and configuration management systems
- DThe change control board is responsible for reviewing and approving changes to the project
Topics
#Change Control Board (CCB)#Change Management#Integrated Change Control#Project Governance