CAPM Question #25: Real Exam Question with Answer & Explanation

The correct answer is D: The change control board is responsible for reviewing and approving changes to the project. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which statement summarizes the role of the change control board?

Options

  • AThe change control board is responsible for presenting the change for approval
  • BThe change control board will analyze the change impact in terms of cost and schedule
  • CThe change control board is responsible for managing the change management and configuration management systems
  • DThe change control board is responsible for reviewing and approving changes to the project

Topics

#Change Control Board (CCB)#Change Management#Integrated Change Control#Project Governance