CAPM · Question #25

Which statement summarizes the role of the change control board?

The correct answer is D. The change control board is responsible for reviewing and approving changes to the project. The Change Control Board (CCB) is the governance body responsible for formally reviewing and approving or rejecting proposed changes to the project.

Predictive, Plan-Based Methodologies

Question

Which statement summarizes the role of the change control board?

Options

  • AThe change control board is responsible for presenting the change for approval
  • BThe change control board will analyze the change impact in terms of cost and schedule
  • CThe change control board is responsible for managing the change management and configuration management systems
  • DThe change control board is responsible for reviewing and approving changes to the project

How the community answered

(32 responses)
  • B
    3% (1)
  • C
    6% (2)
  • D
    91% (29)

Why each option

The Change Control Board (CCB) is the governance body responsible for formally reviewing and approving or rejecting proposed changes to the project.

AThe change control board is responsible for presenting the change for approval

Presenting the change request for approval is the responsibility of the change requestor or project manager, not the CCB itself.

BThe change control board will analyze the change impact in terms of cost and schedule

Analyzing change impact in terms of cost and schedule is performed by the project manager and relevant team members before the request is submitted to the CCB.

CThe change control board is responsible for managing the change management and configuration management systems

Managing the change management and configuration management systems is the responsibility of the project manager, not the CCB.

DThe change control board is responsible for reviewing and approving changes to the projectCorrect

The CCB's primary function is to evaluate submitted change requests and make formal approve or reject decisions, ensuring changes are assessed for alignment with project objectives and that only authorized changes are implemented, as defined in the PMBOK Perform Integrated Change Control process.

Concept tested: Change Control Board role in Perform Integrated Change Control

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Change Control Board (CCB)#Change Management#Integrated Change Control#Project Governance