CAPM · Question #24
A project manager is assigned to a strategic project. Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project. Which…
The correct answer is A. The project and the organization. A project manager's sphere of influence operates primarily within the project itself and the broader organization when seeking senior management support.
Question
Options
- AThe project and the organization
- BThe organization and the industry
- CThe subject matter experts and the project
- DThe change control board and the organization
How the community answered
(37 responses)- A81% (30)
- B5% (2)
- C3% (1)
- D11% (4)
Why each option
A project manager's sphere of influence operates primarily within the project itself and the broader organization when seeking senior management support.
When presenting to senior management for support, the project manager works to influence the project - by securing resources and alignment - and the organization - by gaining executive sponsorship and organizational commitment, which are the two primary spheres of PM influence defined in the PMBOK Guide.
Influencing the industry extends beyond the project manager's typical scope of authority; this is not a standard sphere of PM influence when seeking internal executive support.
Subject matter experts are team-level resources, not a strategic entity the PM seeks to influence when presenting to senior management for project support.
The change control board is an internal governance body, not a separate strategic entity; influencing it alone does not represent the full scope of PM influence at the organizational level.
Concept tested: Project manager spheres of influence
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok