Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

Options

  • APost project artifacts in a transparent fashion and engage stakeholders on a regular basis.
  • BMake surveys among the stakeholders and meet with the team once a month.
  • CCreate a social network and post news there.
  • DCreate personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.