CAPM · Question #23
CAPM Question #23: Real Exam Question with Answer & Explanation
The correct answer is A: Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?
Options
- APost project artifacts in a transparent fashion and engage stakeholders on a regular basis.
- BMake surveys among the stakeholders and meet with the team once a month.
- CCreate a social network and post news there.
- DCreate personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.
Topics
#Agile Communication#Stakeholder Engagement#Transparency#Adaptive Environments