CAPM · Question #231
What is an input to the stakeholder engagement plan?
The correct answer is B. Project charter. The Project Charter is a key input to the Plan Stakeholder Engagement process because it identifies the high-level project description, objectives, key stakeholders, and the project manager's authority - all of which are foundational to understanding who needs to be engaged and…
Question
Options
- ARisk register
- BProject charter
- CScope management plan
- DSchedule management plan
How the community answered
(22 responses)- A5% (1)
- B91% (20)
- C5% (1)
Explanation
The Project Charter is a key input to the Plan Stakeholder Engagement process because it identifies the high-level project description, objectives, key stakeholders, and the project manager's authority - all of which are foundational to understanding who needs to be engaged and how. The project charter establishes stakeholder context before any detailed engagement strategies are formed. The Risk Register (A), Scope Management Plan (C), and Schedule Management Plan (D) may be referenced during the project, but the project charter is the primary foundational document that initiates stakeholder engagement planning.
Topics
Community Discussion