CAPM · Question #230
What two key components of the project management plan are used as inputs to create the cost management plan?
The correct answer is C. Procurement management and schedule management plans. When developing the Cost Management Plan, the project team needs input from the Procurement Management Plan (which defines how vendor contracts and their associated costs will be managed) and the Schedule Management Plan (which determines when costs will be incurred over the…
Question
Options
- ASchedule management and risk management plans
- BSchedule management and scope management plans
- CProcurement management and schedule management plans
- DResource management and schedule management plans
How the community answered
(50 responses)- A8% (4)
- B2% (1)
- C88% (44)
- D2% (1)
Explanation
When developing the Cost Management Plan, the project team needs input from the Procurement Management Plan (which defines how vendor contracts and their associated costs will be managed) and the Schedule Management Plan (which determines when costs will be incurred over the project timeline). Together, these two plans inform how costs will be planned, structured, and monitored. Option A (risk management) and Option D (resource management) are relevant to other cost considerations but are not the primary plan components feeding into cost management plan development in this context.
Topics
Community Discussion
No community discussion yet for this question.