nerdexam
PMIPMI

CAPM · Question #230

CAPM Question #230: Real Exam Question with Answer & Explanation

The correct answer is C: Procurement management and schedule management plans. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What two key components of the project management plan are used as inputs to create the cost management plan?

Options

  • ASchedule management and risk management plans
  • BSchedule management and scope management plans
  • CProcurement management and schedule management plans
  • DResource management and schedule management plans

Topics

#Cost Management#Project Management Plan#Process Inputs#Schedule Management#Procurement Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions