PMIPMI
CAPM · Question #230
CAPM Question #230: Real Exam Question with Answer & Explanation
The correct answer is C: Procurement management and schedule management plans. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What two key components of the project management plan are used as inputs to create the cost management plan?
Options
- ASchedule management and risk management plans
- BSchedule management and scope management plans
- CProcurement management and schedule management plans
- DResource management and schedule management plans
Topics
#Cost Management#Project Management Plan#Process Inputs#Schedule Management#Procurement Management
Community Discussion
No community discussion yet for this question.