CAPM · Question #232

CAPM Question #232: Real Exam Question with Answer & Explanation

The correct answer is C: Parametric estimating. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What tool or technique uses an algorithm or statistical relationship between historical data and other variables to calculate an activity's needed resource quantities?

Options

  • AExpert judgment
  • BBottom-up estimating
  • CParametric estimating
  • DAnalogous estimating

Topics

#Estimating#Parametric Estimating#Resource Estimating#Planning Tools