CAPM · Question #232
CAPM Question #232: Real Exam Question with Answer & Explanation
The correct answer is C: Parametric estimating. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What tool or technique uses an algorithm or statistical relationship between historical data and other variables to calculate an activity's needed resource quantities?
Options
- AExpert judgment
- BBottom-up estimating
- CParametric estimating
- DAnalogous estimating
Topics
#Estimating#Parametric Estimating#Resource Estimating#Planning Tools