What tool or technique uses an algorithm or statistical relationship between historical data and other variables to calculate an activity's needed resource quantities?
Sign in or unlock CAPM to reveal the answer and full explanation for question #232. The question stem and answer options stay visible for context.
Predictive, Plan-Based Methodologies
Question
What tool or technique uses an algorithm or statistical relationship between historical data and other variables to calculate an activity's needed resource quantities?
Options
- AExpert judgment
- BBottom-up estimating
- CParametric estimating
- DAnalogous estimating
Unlock CAPM to see the answer
You've previewed enough free CAPM questions. Unlock CAPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Estimating#Parametric Estimating#Resource Estimating#Planning Tools