CAPM · Question #188
What process is performed periodically throughout the project as needed?
The correct answer is B. Plan Communications Management. Plan Communications Management is performed periodically throughout the project because stakeholder communication needs evolve as the project progresses - stakeholders join or leave, project phases change, and information requirements shift. The PMBOK explicitly notes this proces
Question
Options
- APlan Risk Management
- BPlan Communications Management
- CPlan Resource Management
- DPlan Cost Management
How the community answered
(34 responses)- A9% (3)
- B85% (29)
- C3% (1)
- D3% (1)
Explanation
Plan Communications Management is performed periodically throughout the project because stakeholder communication needs evolve as the project progresses - stakeholders join or leave, project phases change, and information requirements shift. The PMBOK explicitly notes this process is revisited as needed. Plan Risk Management (A), Plan Resource Management (C), and Plan Cost Management (D) are typically performed once during the planning phase and updated only if significant changes occur (via change control). Communications planning's ongoing nature reflects the dynamic relationship between the project team and its stakeholders.
Topics
Community Discussion