nerdexam
PMIPMI

CAPM · Question #189

CAPM Question #189: Real Exam Question with Answer & Explanation

The correct answer is B: Lessons learned. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A project team is closing out a phase and updating the organizational knowledge base. What organizational process asset (OPA) will the team update?

Options

  • ATraceability matrices
  • BLessons learned
  • CChange control procedures
  • DResource availability

Topics

#Lessons Learned#Organizational Process Assets (OPAs)#Project Closure#Knowledge Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions