CAPM · Question #187
What process in Project Risk Management prioritizes project risks?
The correct answer is A. Perform Qualitative Risk Analysis. Perform Qualitative Risk Analysis is specifically defined as the process of prioritizing individual project risks by assessing their probability of occurrence and impact, using a probability and impact matrix. This allows teams to focus attention on high-priority risks. Perform Q
Question
Options
- APerform Qualitative Risk Analysis
- BPerform Quantitative Risk Analysis
- CPlan Risk Responses
- DImplement Risk Responses
How the community answered
(41 responses)- A93% (38)
- C5% (2)
- D2% (1)
Explanation
Perform Qualitative Risk Analysis is specifically defined as the process of prioritizing individual project risks by assessing their probability of occurrence and impact, using a probability and impact matrix. This allows teams to focus attention on high-priority risks. Perform Quantitative Risk Analysis (B) numerically analyzes the combined effect of identified risks on overall project objectives. Plan Risk Responses (C) develops options and actions to address prioritized risks. Implement Risk Responses (D) executes the agreed-upon risk response plans. Prioritization is the defining characteristic of Qualitative Risk Analysis.
Topics