nerdexam
PMI

CAPM · Question #18

During what project management process does the project team begin identifying risks?

The correct answer is B. Planning. Risk identification formally begins during the Planning process group, where the Identify Risks process is first performed as part of Project Risk Management planning.

Predictive, Plan-Based Methodologies

Question

During what project management process does the project team begin identifying risks?

Options

  • AInitiating
  • BPlanning
  • CExecuting
  • DMonitoring and Controlling

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    88% (30)
  • C
    3% (1)
  • D
    6% (2)

Why each option

Risk identification formally begins during the Planning process group, where the Identify Risks process is first performed as part of Project Risk Management planning.

AInitiating

The Initiating process group is focused on authorizing the project and defining it at a high level - it does not include formal risk identification processes.

BPlanningCorrect

The Identify Risks process is part of the Planning process group in PMBOK's Project Risk Management knowledge area, and this is when the project team first conducts a structured effort to identify potential risks and document their characteristics. Beginning risk identification during planning allows the team to incorporate risk responses into the project management plan before execution begins. Risk identification is iterative and continues throughout the project, but the formal start is in the Planning process group.

CExecuting

Executing is too late to begin the initial identification of risks, as risk responses should already be planned before work commences.

DMonitoring and Controlling

Monitoring and Controlling involves monitoring identified risks and identifying new risks as the project progresses, but the initial formal identification starts in Planning.

Concept tested: When risk identification begins in the project life cycle

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project Risk Management#PMI Process Groups#Identify Risks#Planning Process Group

Community Discussion

No community discussion yet for this question.

Full CAPM Practice