nerdexam
PMIPMI

CAPM · Question #17

CAPM Question #17: Real Exam Question with Answer & Explanation

The correct answer is B: Communications management plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should the project manager consult?

Options

  • ARisk management plan
  • BCommunications management plan
  • CChange management plan
  • DStakeholder engagement plan

Topics

#Communications Management#Issue Escalation#Project Plans#Stakeholder Communication

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions