CAPM · Question #16
CAPM Question #16: Real Exam Question with Answer & Explanation
The correct answer is D: Prioritize each project risk and assign the probability of occurrence and impact for each one. See the full explanation below for the reasoning.
Predictive Plan-Based Methodologies
Question
Which of the following tasks is related to the Perform Qualitative Risk Analysis process?
Options
- AIdentify the project risks and assign a probability of occurrence
- BPerform a sensitivity analysis to determine which risk has the most potential for impacting the project
- CAnalyze the effect of identified project risks as numerical data
- DPrioritize each project risk and assign the probability of occurrence and impact for each one
Topics
#Risk Management#Qualitative Risk Analysis#Project Risk#PMBOK Processes