nerdexam
PMIPMI

CAPM · Question #16

CAPM Question #16: Real Exam Question with Answer & Explanation

The correct answer is D: Prioritize each project risk and assign the probability of occurrence and impact for each one. See the full explanation below for the reasoning.

Predictive Plan-Based Methodologies

Question

Which of the following tasks is related to the Perform Qualitative Risk Analysis process?

Options

  • AIdentify the project risks and assign a probability of occurrence
  • BPerform a sensitivity analysis to determine which risk has the most potential for impacting the project
  • CAnalyze the effect of identified project risks as numerical data
  • DPrioritize each project risk and assign the probability of occurrence and impact for each one

Topics

#Risk Management#Qualitative Risk Analysis#Project Risk#PMBOK Processes

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions