nerdexam
PMIPMI

CAPM · Question #179

CAPM Question #179: Real Exam Question with Answer & Explanation

The correct answer is A: It represents how and when the project will deliver the products, services, and results defined in the project scope. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

Options

  • AIt represents how and when the project will deliver the products, services, and results defined in the project scope
  • BIt creates a formal record of the project and shows the organizational commitment to the project
  • CIt describes how the scope will be defined, developed, monitored, controlled, and validated
  • DIt provides the needs of a stakeholders or stakeholder group

Topics

#Project schedule#Schedule purpose#Project planning#Project deliverables

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions