PMIPMI
CAPM · Question #179
CAPM Question #179: Real Exam Question with Answer & Explanation
The correct answer is A: It represents how and when the project will deliver the products, services, and results defined in the project scope. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?
Options
- AIt represents how and when the project will deliver the products, services, and results defined in the project scope
- BIt creates a formal record of the project and shows the organizational commitment to the project
- CIt describes how the scope will be defined, developed, monitored, controlled, and validated
- DIt provides the needs of a stakeholders or stakeholder group
Topics
#Project schedule#Schedule purpose#Project planning#Project deliverables
Community Discussion
No community discussion yet for this question.