PMIPMI
CAPM · Question #180
CAPM Question #180: Real Exam Question with Answer & Explanation
The correct answer is C: Plan Cost Management, Estimate Costs, Determine Budget, Control Costs. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following are processes associated with Project Cost Management?
Options
- ADevelop Costs, Estimate Costs, Determine Budget, Control Costs
- BDevelop Budget, Determine Budget, Determine Risks, Control Costs
- CPlan Cost Management, Estimate Costs, Determine Budget, Control Costs
- DPlan Budget Management, Determine Budget, Create Cost Accounts, Control Costs
Topics
#Project Cost Management#Cost Management Processes#PMBOK Guide
Community Discussion
No community discussion yet for this question.