nerdexam
PMIPMI

CAPM · Question #180

CAPM Question #180: Real Exam Question with Answer & Explanation

The correct answer is C: Plan Cost Management, Estimate Costs, Determine Budget, Control Costs. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which of the following are processes associated with Project Cost Management?

Options

  • ADevelop Costs, Estimate Costs, Determine Budget, Control Costs
  • BDevelop Budget, Determine Budget, Determine Risks, Control Costs
  • CPlan Cost Management, Estimate Costs, Determine Budget, Control Costs
  • DPlan Budget Management, Determine Budget, Create Cost Accounts, Control Costs

Topics

#Project Cost Management#Cost Management Processes#PMBOK Guide

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions