nerdexam
PMI

CAPM · Question #178

When should Project Risk Management be conducted?

The correct answer is D. Throughout the project lifecycle. Project Risk Management is not a one-time activity limited to planning; it must be performed continuously throughout the entire project lifecycle to remain effective.

Project Management Fundamentals and Core Concepts

Question

When should Project Risk Management be conducted?

Options

  • AProject Planning
  • BMonitoring and Controlling
  • CQuality Planning
  • DThroughout the project lifecycle

How the community answered

(27 responses)
  • A
    4% (1)
  • C
    7% (2)
  • D
    89% (24)

Why each option

Project Risk Management is not a one-time activity limited to planning; it must be performed continuously throughout the entire project lifecycle to remain effective.

AProject Planning

Conducting risk management only during project planning would miss risks that emerge during execution, monitoring, and closing phases of the project.

BMonitoring and Controlling

Limiting risk management to Monitoring and Controlling ignores the critical risk identification and planning activities that must occur in earlier phases.

CQuality Planning

Quality planning is a distinct process from risk management, and restricting risk activities to only that context is both too narrow and incorrect per the PMBOK Guide.

DThroughout the project lifecycleCorrect

The PMBOK Guide explicitly states that risk management should be conducted throughout the entire project lifecycle because new risks emerge, existing risks change in probability or impact, and responses need monitoring as the project progresses. Limiting risk management to a single phase would leave unidentified risks unaddressed and allow known risks to go unmonitored.

Concept tested: Continuous nature of Project Risk Management

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project Risk Management#Project Lifecycle#Continuous Process

Community Discussion

No community discussion yet for this question.

Full CAPM Practice