PMIPMI
CAPM · Question #147
CAPM Question #147: Real Exam Question with Answer & Explanation
The correct answer is B: Manage Communications. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Project reporting is a tool that is most closely associated with which process?
Options
- ACommunicate Plan
- BManage Communications
- CReport Performance
- DControl Communications
Topics
#Project Communications Management#Manage Communications process#Project reporting#PMBOK Tools & Techniques
Community Discussion
No community discussion yet for this question.