The correct answer is B: Manage Communications. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Project reporting is a tool that is most closely associated with which process?

Options

  • ACommunicate Plan
  • BManage Communications
  • CReport Performance
  • DControl Communications

Topics

#Project Communications Management#Manage Communications process#Project reporting#PMBOK Tools & Techniques