PMIPMI
CAPM · Question #148
CAPM Question #148: Real Exam Question with Answer & Explanation
The correct answer is B: 1.12. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project reports an earned value (EV) of US$45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?
Options
- A0.88
- B1.12
- C0.58
- D1.58
Topics
#Earned Value Management#Cost Performance Index#Project Cost Management#Performance Measurement
Community Discussion
No community discussion yet for this question.