nerdexam
PMIPMI

CAPM · Question #148

CAPM Question #148: Real Exam Question with Answer & Explanation

The correct answer is B: 1.12. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project reports an earned value (EV) of US$45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

Options

  • A0.88
  • B1.12
  • C0.58
  • D1.58

Topics

#Earned Value Management#Cost Performance Index#Project Cost Management#Performance Measurement

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions