CAPM · Question #146

CAPM Question #146: Real Exam Question with Answer & Explanation

The correct answer is C: Sole source. See the full explanation below for the reasoning.

Predictive Plan-Based Methodologies

Question

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

Options

  • ALeast cost
  • BQualifications only
  • CSole source
  • DFixed budget

Topics

#Procurement Management#Source Selection Methods#Sole Source