PMIPMI
CAPM · Question #146
CAPM Question #146: Real Exam Question with Answer & Explanation
The correct answer is C: Sole source. See the full explanation below for the reasoning.
Predictive Plan-Based Methodologies
Question
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?
Options
- ALeast cost
- BQualifications only
- CSole source
- DFixed budget
Topics
#Procurement Management#Source Selection Methods#Sole Source
Community Discussion