The primary purpose of the stakeholder register is to:

The correct answer is C. Maintain a list of all project stakeholders. The stakeholder register is the primary artifact for documenting and tracking all identified project stakeholders. Other project documents serve different tracking purposes.

Predictive, Plan-Based Methodologies

Question

The primary purpose of the stakeholder register is to:

Options

  • ARecord stakeholder issues on the project
  • BMaintain lessons learned earlier in the project
  • CMaintain a list of all project stakeholders
  • DDocument change requests and their status

How the community answered

(31 responses)
  • B
    3% (1)
  • C
    94% (29)
  • D
    3% (1)

Why each option

The stakeholder register is the primary artifact for documenting and tracking all identified project stakeholders. Other project documents serve different tracking purposes.

ARecord stakeholder issues on the project

Stakeholder issues are recorded in the issue log, not the stakeholder register.

BMaintain lessons learned earlier in the project

Lessons learned are captured in the lessons learned register, which is maintained throughout the project.

CMaintain a list of all project stakeholdersCorrect

The stakeholder register is created during the Identify Stakeholders process and serves as the central document maintaining a list of all project stakeholders along with their identification information, assessment details, and classification. It is updated throughout the project as new stakeholders are identified or their information changes.

DDocument change requests and their status

Change requests and their status are tracked in the change log, a separate project document.

Concept tested: Purpose and content of the stakeholder register

Topics

#Stakeholder Management#Project Documents#Stakeholder Register#Project Planning