Question
The primary purpose of the stakeholder register is to:
Options
- ARecord stakeholder issues on the project
- BMaintain lessons learned earlier in the project
- CMaintain a list of all project stakeholders
- DDocument change requests and their status
Topics
#Stakeholder Management#Project Documents#Stakeholder Register#Project Planning