CAPM Question #145: Real Exam Question with Answer & Explanation

The correct answer is C: Maintain a list of all project stakeholders. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

The primary purpose of the stakeholder register is to:

Options

  • ARecord stakeholder issues on the project
  • BMaintain lessons learned earlier in the project
  • CMaintain a list of all project stakeholders
  • DDocument change requests and their status

Topics

#Stakeholder Management#Project Documents#Stakeholder Register#Project Planning