CAPM · Question #144

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

The correct answer is D. Knowledge management. The PMBOK Guide identifies specific tailoring considerations for the Project Cost Management knowledge area. Knowledge management is one of the listed considerations.

Predictive, Plan-Based Methodologies

Question

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

Options

  • ADiversity background
  • BStakeholder's relationships
  • CTechnical expertise
  • DKnowledge management

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    3% (1)
  • D
    88% (29)

Why each option

The PMBOK Guide identifies specific tailoring considerations for the Project Cost Management knowledge area. Knowledge management is one of the listed considerations.

ADiversity background

Diversity background is not a listed tailoring consideration for Project Cost Management in the PMBOK Guide.

BStakeholder's relationships

Stakeholder relationships are relevant to stakeholder management tailoring, not specifically to cost management tailoring.

CTechnical expertise

Technical expertise is not listed as a standard tailoring consideration for the Project Cost Management knowledge area.

DKnowledge managementCorrect

Knowledge management is explicitly listed as a tailoring consideration for Project Cost Management in the PMBOK Guide. It addresses how the organization retains and applies cost-related knowledge and whether knowledge management systems will influence how costs are estimated, tracked, or reported across projects.

Concept tested: Tailoring considerations for Project Cost Management

Topics

#Project Cost Management#Process Tailoring#Knowledge Management#Organizational Process Assets