nerdexam
PMIPMI

CAPM · Question #139

CAPM Question #139: Real Exam Question with Answer & Explanation

The correct answer is B: Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which tasks should a project manager perform in order to manage the project schedule effectively?

Options

  • APlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Develop Schedule
  • BPlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule
  • CPlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities, Develop Schedule
  • DDefine Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Estimate Cost of Activities, Develop Schedule

Topics

#Schedule Management#PMBOK Processes#Project Planning#Project Controlling

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions