PMIPMI
CAPM · Question #139
CAPM Question #139: Real Exam Question with Answer & Explanation
The correct answer is B: Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which tasks should a project manager perform in order to manage the project schedule effectively?
Options
- APlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Develop Schedule
- BPlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule
- CPlan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities, Develop Schedule
- DDefine Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Estimate Cost of Activities, Develop Schedule
Topics
#Schedule Management#PMBOK Processes#Project Planning#Project Controlling
Community Discussion
No community discussion yet for this question.