PMIPMI
CAPM · Question #140
CAPM Question #140: Real Exam Question with Answer & Explanation
The correct answer is B: Build a team that can respond to changes within a collaborative, decision-making environment. See the full explanation below for the reasoning.
Agile Frameworks/Methodologies
Question
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
Options
- ATake control of all decisions and product planning
- BBuild a team that can respond to changes within a collaborative, decision-making environment
- CPromote a team with a narrow specialization within a hierarchical environment
- DDelegate project decisions to the product owner and sponsor
Topics
#Agile Project Management#Project Integration Management#Agile Teams#Collaboration
Community Discussion
No community discussion yet for this question.