nerdexam
PMI

CAPM · Question #138

What does expert judgement provide as an input to the resource management plan?

The correct answer is C. Estimated lead times based on lessons learned. Expert judgment contributes estimated lead times drawn from lessons learned as a key input when developing the resource management plan.

Predictive, Plan-Based Methodologies

Question

What does expert judgement provide as an input to the resource management plan?

Options

  • AGeographic distribution of facilities and resources
  • BPhysical resource management policies and procedures
  • CEstimated lead times based on lessons learned
  • DTemplates for the resource management plan

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    85% (22)
  • D
    8% (2)

Why each option

Expert judgment contributes estimated lead times drawn from lessons learned as a key input when developing the resource management plan.

AGeographic distribution of facilities and resources

Geographic distribution of facilities and resources is an enterprise environmental factor (EEF) that serves as an input to resource planning, not something provided specifically by expert judgment.

BPhysical resource management policies and procedures

Physical resource management policies and procedures are organizational process assets (OPAs), not outputs of expert judgment applied during planning.

CEstimated lead times based on lessons learnedCorrect

Experts with prior project experience bring knowledge of how long it typically takes to acquire, onboard, or transition resources - including lead times for procurement or staffing actions. This historical perspective, rooted in lessons learned, directly informs realistic resource planning decisions that could not otherwise be estimated without domain experience.

DTemplates for the resource management plan

Templates for the resource management plan are also organizational process assets - pre-existing artifacts available to the team - not something expert judgment generates.

Concept tested: Expert judgment contribution to resource management planning

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Expert Judgment#Resource Management Plan#Project Planning#Inputs and Outputs

Community Discussion

No community discussion yet for this question.

Full CAPM Practice