Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

The correct answer is B. Project versions are mandatory for Milestone Trend Analysis (MTA) C. Project versions can be created automatically based on user status. Project versions are copies of projects that allow you to save snapshots of project data at different points in time. Project versions are mandatory for Milestone Trend Analysis (MTA), which is a tool that allows you to monitor and compare the planned and actual dates of…

Project Planning

Question

Which of the following statements apply to project versions? Note: There are 2 correct answers to this question

Options

  • AProject versions can be changed
  • BProject versions are mandatory for Milestone Trend Analysis (MTA)
  • CProject versions can be created automatically based on user status
  • DManually Created project versions always require a project version profile

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    92% (23)
  • D
    4% (1)

Explanation

Project versions are copies of projects that allow you to save snapshots of project data at different points in time. Project versions are mandatory for Milestone Trend Analysis (MTA), which is a tool that allows you to monitor and compare the planned and actual dates of milestones in a project over time. Project versions can be created automatically based on user status, which means that you can define rules that trigger the creation of project versions when certain user statuses are set for project objects.