nerdexam
SAP

C_TS412_2021 · Question #118

Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

The correct answer is A. Planned revenue requires a sales order assigned to a WBS element D. Actual revenue is posted via a billing document created from a sales order. Planned revenue and actual revenue are two types of revenue for WBS elements in SAP Project System. Planned revenue requires a sales order assigned to a WBS element, which means that the sales order item contains the data for revenue planning, such as quantity, price, and…

Costs and Revenues in Project Systems

Question

Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

Options

  • APlanned revenue requires a sales order assigned to a WBS element
  • BPlanned revenue can be transferred from a sales quotation
  • CActual revenue is posted via a billing plan assigned to a WBS element
  • DActual revenue is posted via a billing document created from a sales order

How the community answered

(22 responses)
  • A
    77% (17)
  • B
    18% (4)
  • C
    5% (1)

Explanation

Planned revenue and actual revenue are two types of revenue for WBS elements in SAP Project System. Planned revenue requires a sales order assigned to a WBS element, which means that the sales order item contains the data for revenue planning, such as quantity, price, and billing plan. Actual revenue is posted via a billing document created from a sales order, which means that the billing document records the delivery of goods or services to a customer and requests payment for them.

Topics

#planned revenue#actual revenue#sales quotation#billing document

Community Discussion