C_TS412_2021 · Question #118
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question
The correct answer is A. Planned revenue requires a sales order assigned to a WBS element D. Actual revenue is posted via a billing document created from a sales order. Planned revenue and actual revenue are two types of revenue for WBS elements in SAP Project System. Planned revenue requires a sales order assigned to a WBS element, which means that the sales order item contains the data for revenue planning, such as quantity, price, and…
Question
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question
Options
- APlanned revenue requires a sales order assigned to a WBS element
- BPlanned revenue can be transferred from a sales quotation
- CActual revenue is posted via a billing plan assigned to a WBS element
- DActual revenue is posted via a billing document created from a sales order
How the community answered
(22 responses)- A77% (17)
- B18% (4)
- C5% (1)
Explanation
Planned revenue and actual revenue are two types of revenue for WBS elements in SAP Project System. Planned revenue requires a sales order assigned to a WBS element, which means that the sales order item contains the data for revenue planning, such as quantity, price, and billing plan. Actual revenue is posted via a billing document created from a sales order, which means that the billing document records the delivery of goods or services to a customer and requests payment for them.