nerdexam
SAP

C_TS412_2021 · Question #120

Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

The correct answer is A. An activated Scheduling indicator in the control key of the internal processing activity D. The relationships between activity elements E. The factory calendar in the work center used for the internal processing activity. The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or…

Project Planning

Question

Which of the following factors influence the scheduling of internal processing activities? Note:

There are 3 correct answers to this question

Options

  • AAn activated Scheduling indicator in the control key of the internal processing activity
  • BWhether the work for the internal activity is greater than its duration
  • CThe unit (for example, hour, day) of the field Normal Duration field of the activity
  • DThe relationships between activity elements
  • EThe factory calendar in the work center used for the internal processing activity

How the community answered

(22 responses)
  • A
    73% (16)
  • B
    9% (2)
  • C
    18% (4)

Explanation

The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The scheduling indicator in the control key determines whether an activity is included in scheduling or not. The activity elements are subordinate units of an activity that represent partial tasks or work packages. The relationships between activity elements define the logical sequence and dependencies of the partial tasks. The factory calendar is a parameter that defines the working days and holidays for a work center. The factory calendar affects the duration and dates of an activity that uses the work center. Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially Cisco, Microsoft, CompTIA, Citrix, EMC, HP, Oracle, VMware, Juniper, Check Point, LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.

Topics

#internal activity scheduling#control key#factory calendar#activity relationships

Community Discussion

No community discussion yet for this question.

Full C_TS412_2021 Practice