840-423 · Question #9

Which statement describes a risk that is associated with relying on a customer's IT department?

The correct answer is A. The timeframe for executing the tasks may be longer than if Cisco or a Partner did this work. Relying on a customer's IT department introduces scheduling risk - their teams juggle competing internal priorities, meaning implementation tasks often get deprioritized or delayed compared to a dedicated Cisco or Partner team focused solely on the engagement. This is the core…

Creating and Presenting Comprehensive Business Cases

Question

Which statement describes a risk that is associated with relying on a customer's IT department?

Options

  • AThe timeframe for executing the tasks may be longer than if Cisco or a Partner did this work.
  • BThe business unit executive uncovers that the solution required some customization, tailoring,
  • CThe IT executive takes credit for an activity which Cisco or the Partner should have executed.
  • DThe total cost of implementation is lower than you originally anticipated.

How the community answered

(21 responses)
  • A
    81% (17)
  • B
    10% (2)
  • C
    5% (1)
  • D
    5% (1)

Explanation

Relying on a customer's IT department introduces scheduling risk - their teams juggle competing internal priorities, meaning implementation tasks often get deprioritized or delayed compared to a dedicated Cisco or Partner team focused solely on the engagement. This is the core risk: timeline slippage due to competing demands on internal IT resources.

Why the distractors are wrong:

  • B is incorrect because a business unit executive discovering customization is a project scope/communication issue, not a risk specific to relying on IT staff.
  • C is incorrect because credit-taking is a political/relationship concern, not a meaningful delivery risk in this context.
  • D is incorrect because lower-than-expected costs would actually be a positive outcome, not a risk.

Memory tip: Think "IT = Internal Ties" - the customer's IT team is tied to internal commitments that will always compete with your project, making delays the most realistic risk when depending on them.

Topics

#Implementation Risk#Resource Capacity#Project Timeline#Vendor vs. Internal