Which option best reflects information that must be captured before you create the business case?

The correct answer is B. estimate of investment required: initial investment, recurring for each period, and specific to. Option B is correct because a business case fundamentally requires a structured financial foundation: you must capture the initial investment, ongoing periodic costs, and any period-specific costs before you can build a credible case for moving forward - without these, you…

Creating and Presenting Comprehensive Business Cases

Question

Which option best reflects information that must be captured before you create the business case?

Options

  • Acustomer's budget and expectations for ROI
  • Bestimate of investment required: initial investment, recurring for each period, and specific to
  • Cassessment of the customer's procurement process
  • Ddetailed analysis of cost savings that results from a pilot

How the community answered

(53 responses)
  • A
    15% (8)
  • B
    77% (41)
  • C
    6% (3)
  • D
    2% (1)

Explanation

Option B is correct because a business case fundamentally requires a structured financial foundation: you must capture the initial investment, ongoing periodic costs, and any period-specific costs before you can build a credible case for moving forward - without these, you cannot calculate ROI, justify the project, or compare alternatives.

Why the distractors are wrong:

  • A is backwards - the customer's budget and ROI expectations are inputs you use to validate the business case, not prerequisites you capture before building it. ROI is calculated within the business case itself.
  • C (procurement process) is operational context relevant to executing a purchase, not to building the financial justification for one.
  • D (detailed pilot cost-savings analysis) comes after a pilot has run - you don't have this data before the business case; a pilot is often authorized by the business case.

Memory tip: Think of the business case as a financial blueprint. You can't draw blueprints without knowing the cost of materials first - Option B gives you the raw cost structure (initial + recurring + period-specific) that every other calculation in the business case depends on.

Topics