840-423 · Question #27
Which option is a governance approach for a project?
The correct answer is A. a process for approving changes. Project governance refers to the framework of rules, processes, and decision-making structures that guide how a project is directed and controlled. Option A - a process for approving changes - is correct because change control is a core governance mechanism: it defines who has…
Question
Which option is a governance approach for a project?
Options
- Aa process for approving changes
- Ban annual strategy planning session
- Cinformal surveys
- Da job description for network architect
How the community answered
(24 responses)- A92% (22)
- B4% (1)
- D4% (1)
Explanation
Project governance refers to the framework of rules, processes, and decision-making structures that guide how a project is directed and controlled. Option A - a process for approving changes - is correct because change control is a core governance mechanism: it defines who has authority to approve changes, how requests are evaluated, and what criteria must be met, ensuring accountability and oversight.
Option B (annual strategy planning) is a strategic planning activity, not project governance - it operates at the organizational level, not the project level. Option C (informal surveys) is a feedback-gathering technique, lacking the formal authority or control structure that governance requires. Option D (a job description for a network architect) is an HR/organizational artifact, not a mechanism for directing or controlling a project.
Memory tip: Think of governance as "guardrails with gatekeepers" - if an option describes a formal process that controls who decides what and how, it's governance. Change approval fits perfectly; the other options describe planning, opinions, or roles.