840-423 · Question #26
Which option is a governance approach for a project?
The correct answer is A. committee of stakeholder reps. A committee of stakeholder representatives (A) is a governance approach because governance is about decision-making authority, oversight, and accountability - a committee structure embodies all three by bringing together those with a stake in the project to guide and control…
Question
Which option is a governance approach for a project?
Options
- Acommittee of stakeholder reps
- Bmeasurements of system security
- Coperating procedures for data backup
- Dstatus reports on total IT systems
How the community answered
(39 responses)- A95% (37)
- C3% (1)
- D3% (1)
Explanation
A committee of stakeholder representatives (A) is a governance approach because governance is about decision-making authority, oversight, and accountability - a committee structure embodies all three by bringing together those with a stake in the project to guide and control it.
Why the distractors are wrong:
- B (security measurements) describes a security control/metric, not a governance structure.
- C (data backup procedures) is an operational procedure - it's about executing work, not overseeing or directing it.
- D (IT status reports) is a reporting/monitoring activity - useful input to governance, but not governance itself.
Memory tip: Think of governance as "who decides and who is accountable." Only option A describes a group of people with authority - the others are tools, procedures, or reports that governance bodies use, not governance itself.