Which option is a governance approach for a project?

The correct answer is A. committee of stakeholder reps. A committee of stakeholder representatives (A) is a governance approach because governance is about decision-making authority, oversight, and accountability - a committee structure embodies all three by bringing together those with a stake in the project to guide and control…

Creating and Presenting Comprehensive Business Cases

Question

Which option is a governance approach for a project?

Options

  • Acommittee of stakeholder reps
  • Bmeasurements of system security
  • Coperating procedures for data backup
  • Dstatus reports on total IT systems

How the community answered

(39 responses)
  • A
    95% (37)
  • C
    3% (1)
  • D
    3% (1)

Explanation

A committee of stakeholder representatives (A) is a governance approach because governance is about decision-making authority, oversight, and accountability - a committee structure embodies all three by bringing together those with a stake in the project to guide and control it.

Why the distractors are wrong:

  • B (security measurements) describes a security control/metric, not a governance structure.
  • C (data backup procedures) is an operational procedure - it's about executing work, not overseeing or directing it.
  • D (IT status reports) is a reporting/monitoring activity - useful input to governance, but not governance itself.

Memory tip: Think of governance as "who decides and who is accountable." Only option A describes a group of people with authority - the others are tools, procedures, or reports that governance bodies use, not governance itself.