840-423 · Question #23
Which option is part of an implementation strategy?
The correct answer is B. completion criteria for major work packages that are dependent on other projects. Option B is correct because an implementation strategy outlines how a project or system will be executed, including the sequencing of work, dependencies between components, and the criteria that must be met before moving forward - all of which directly apply to completion…
Question
Which option is part of an implementation strategy?
Options
- Anames of employees and their user IDs
- Bcompletion criteria for major work packages that are dependent on other projects
- Cname of the finance rep who is responsible for tracking costs
- Dresponse time requirements for executive quarterly update videos
How the community answered
(35 responses)- A9% (3)
- B74% (26)
- C14% (5)
- D3% (1)
Explanation
Option B is correct because an implementation strategy outlines how a project or system will be executed, including the sequencing of work, dependencies between components, and the criteria that must be met before moving forward - all of which directly apply to completion criteria for dependent work packages.
Why the distractors are wrong:
- A (employee names and user IDs) belongs in an access management list or organizational directory, not an implementation strategy.
- C (name of the finance rep) is a staffing or RACI assignment detail - it identifies who, not how.
- D (response time requirements for videos) is a performance/service-level requirement for a specific deliverable, not a strategic implementation concern.
Memory tip: Think of an implementation strategy as answering "How do we execute and in what order?" - anything about sequencing, dependencies, or completion gates fits. Names of people and technical performance specs belong in other documents (org charts, SLAs, staffing plans).