You receive an e-mail message that contains a list of tasks. You need to create a new project schedule from the list of tasks. What should you do first?
The correct answer is C. Create a new file in Project 2010 and paste the list of tasks. See the full explanation below for the reasoning.
Question
You receive an e-mail message that contains a list of tasks. You need to create a new project schedule from the list of tasks. What should you do first?
Options
- AOpen a previously saved Project 2010 file and save it as a blank template.
- BCreate a list of tasks in Microsoft Excel, and save the file by using the .mpt file extension.
- CCreate a new file in Project 2010 and paste the list of tasks.
- DCreate a new template file in Project 2010.
How the community answered
(32 responses)- A6% (2)
- B3% (1)
- C81% (26)
- D9% (3)