You receive an e-mail message that contains a list of tasks. You need to create a new project schedule from the list of tasks. What should you do first?

The correct answer is C. Create a new file in Project 2010 and paste the list of tasks. See the full explanation below for the reasoning.

Question

You receive an e-mail message that contains a list of tasks. You need to create a new project schedule from the list of tasks. What should you do first?

Options

  • AOpen a previously saved Project 2010 file and save it as a blank template.
  • BCreate a list of tasks in Microsoft Excel, and save the file by using the .mpt file extension.
  • CCreate a new file in Project 2010 and paste the list of tasks.
  • DCreate a new template file in Project 2010.

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    81% (26)
  • D
    9% (3)