The correct answer is C. Use the New from SharePoint feature and type the URL that contains the task list.. See the full explanation below for the reasoning.
Question
You need to import a task list from a Microsoft Office SharePoint 2010 site to create a project schedule in Project 2010. You need to achieve this goal while maintaining SharePoint synchronization. What should you do?
Options
- AUse the Save to SharePoint feature and type the URL that contains the task list.
- BOpen the SharePoint task list in Datasheet view and copy the tasks to a blank project file.
- CUse the New from SharePoint feature and type the URL that contains the task list.
- DSave the SharePoint task list to a Microsoft Excel file and use the Project Import Wizard.