You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use?
The correct answer is C. Insert Summary. See the full explanation below for the reasoning.
Question
You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use?
Options
- AOutdent
- BFill Down
- CInsert Summary
- DMove Task
How the community answered
(55 responses)- A7% (4)
- B5% (3)
- C73% (40)
- D15% (8)