70-178 · Question #69

You are creating a project schedule in Microsoft Office Project Standard 2010. One of the five project tasks can be worked on only at night. You need to ensure that the resources assigned to this…

The correct answer is D. Apply the Night Shift calendar to the task, and then ensure that Project will ignore resource. See the full explanation below for the reasoning.

Question

You are creating a project schedule in Microsoft Office Project Standard 2010. One of the five project tasks can be worked on only at night. You need to ensure that the resources assigned to this task are scheduled to work during the night shift. What should you do?

Options

  • ASet the appropriate overnight working times as an exception in the project calendar.
  • BSet the appropriate overnight working times as an exception in the Night Shift calendar.
  • CApply the Night Shift calendar to the task, and then ensure that the task is effort-driven with
  • DApply the Night Shift calendar to the task, and then ensure that Project will ignore resource

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    9% (3)
  • D
    81% (26)