70-178 · Question #21

You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?

The correct answer is D. Create a custom table and a custom view. See the full explanation below for the reasoning.

Question

You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?

Options

  • ACreate a custom filter and a custom view.
  • BCreate a custom table and a custom group.
  • CCreate a custom filter and a custom table.
  • DCreate a custom table and a custom view.

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    5% (1)
  • C
    5% (1)
  • D
    80% (16)