70-178 · Question #21
You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?
The correct answer is D. Create a custom table and a custom view. See the full explanation below for the reasoning.
Question
You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?
Options
- ACreate a custom filter and a custom view.
- BCreate a custom table and a custom group.
- CCreate a custom filter and a custom table.
- DCreate a custom table and a custom view.
How the community answered
(20 responses)- A10% (2)
- B5% (1)
- C5% (1)
- D80% (16)