70-178 · Question #20
In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information: - Tasks that are not started. - Tasks in progress. - Tasks that have…
The correct answer is A. Select Group by Complete and Incomplete Tasks, and then add the Remaining Work field to the. See the full explanation below for the reasoning.
Question
In the default Gantt Chart view of your Project Professional 2010 project, you need to display the following information:
- Tasks that are not started.
- Tasks in progress.
- Tasks that have finished.
- Total remaining effort for each group of tasks.
What should you do on the View tab?
Options
- ASelect Group by Complete and Incomplete Tasks, and then add the Remaining Work field to the
- BSelect Group by Complete and Incomplete Tasks, and then add the Work field to the table.
- CSelect Group by Active v. Inactive, and then add the Remaining Work field to the table.
- DSelect Group by Active v. Inactive, and then add the Work field to the table.
How the community answered
(52 responses)- A73% (38)
- B10% (5)
- C13% (7)
- D4% (2)