You create a new Gantt Chart view. You need to copy the view to a different project. What should you do?

The correct answer is B. Use the Organizer tool. The Organizer is a dialog box that allows you to copy custom elements (incl. views, reports, tables, filters, groups) between files, or between a file and the global template.

Planning a Project

Question

You create a new Gantt Chart view. You need to copy the view to a different project. What should you do?

Options

  • AUse the Links Between Projects tool.
  • BUse the Organizer tool.
  • CUse the Save Views feature.
  • DUse the Compare Projects feature.

How the community answered

(23 responses)
  • B
    83% (19)
  • C
    13% (3)
  • D
    4% (1)

Explanation

The Organizer is a dialog box that allows you to copy custom elements (incl. views, reports, tables, filters, groups) between files, or between a file and the global template.

Topics

#Organizer tool#view management#Gantt chart view#project templates