70-178 · Question #6
You have a list of tasks in Microsoft Excel 2010. You need to create a Microsoft Project 2010 schedule that maintains the order of the tasks. Which two actions could you perform? (Each correct…
Sign in or unlock 70-178 to reveal the answer and full explanation for question #6. The question stem and answer options stay visible for context.
Planning a Project
Question
You have a list of tasks in Microsoft Excel 2010. You need to create a Microsoft Project 2010 schedule that maintains the order of the tasks. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)
Options
- AFrom Excel 2010, save the file by using the .mpp file extension.
- BFrom Project 2010, use the New from Excel workbook wizard.
- CFrom Project 2010, use the Open command and select the Excel file.
- DFrom Excel 2010, save the file by using the .mpt file extension.
Unlock 70-178 to see the answer
You've previewed enough free 70-178 questions. Unlock 70-178 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Excel import#schedule creation#file format#task import