Question

You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?

Options

  • AUse a work type resource.
  • BCreate a custom field and capture travel costs at the project level.
  • CUse a budget resource.
  • DUse a cost type resource.