70-178 · Question #27
You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?
The correct answer is D. Use a cost type resource. The currency value of cost resources does not depend on the amount of work done on or the duration of the task that they are assigned to.
Planning a Project
Question
You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task. What should you do?
Options
- AUse a work type resource.
- BCreate a custom field and capture travel costs at the project level.
- CUse a budget resource.
- DUse a cost type resource.
How the community answered
(50 responses)- A8% (4)
- B4% (2)
- C18% (9)
- D70% (35)
Explanation
The currency value of cost resources does not depend on the amount of work done on or the duration of the task that they are assigned to.
Topics
#cost resource#resource types#task-level costs#airfare tracking