70-178 · Question #26
You are reviewing the task details of your project. You receive the following warning message: "This task has resources assigned which are over-allocated." You need to be able to identify a possible…
The correct answer is D. Use the Task Inspector tool. See the full explanation below for the reasoning.
Question
You are reviewing the task details of your project. You receive the following warning message:
"This task has resources assigned which are over-allocated." You need to be able to identify a possible resolution for the over-allocated resources. What should you do?
Options
- AChange the task type to Fixed Work, and then recalculate the project.
- BChange the task type to Fixed Units, and then recalculate the project.
- CIncrease the task duration values for the task.
- DUse the Task Inspector tool.
- ESet the Level Assignments flag to Yes for the task, and then recalculate the schedule.
How the community answered
(50 responses)- A14% (7)
- B2% (1)
- C8% (4)
- D72% (36)
- E4% (2)