70-178 · Question #25

You have an unscheduled, unassigned task in your Project Professional 2010 schedule. You identify an available resource. You need to assign the task to the resource without scheduling the task. What…

The correct answer is C. Use the Team Planner view. See the full explanation below for the reasoning.

Question

You have an unscheduled, unassigned task in your Project Professional 2010 schedule. You identify an available resource. You need to assign the task to the resource without scheduling the task. What should you do?

Options

  • AUse the Replace feature in the Assign Resources dialog box.
  • BUse the Add Resources function.
  • CUse the Team Planner view.
  • DUse the Calendar view.

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    17% (4)
  • C
    71% (17)
  • D
    4% (1)