Microsoft
70-178 · Question #25
70-178 Question #25: Real Exam Question with Answer & Explanation
The correct answer is C. Use the Team Planner view.. See the full explanation below for the reasoning.
Question
You have an unscheduled, unassigned task in your Project Professional 2010 schedule. You identify an available resource. You need to assign the task to the resource without scheduling the task. What should you do?
Options
- AUse the Replace feature in the Assign Resources dialog box.
- BUse the Add Resources function.
- CUse the Team Planner view.
- DUse the Calendar view.
Community Discussion
No community discussion yet for this question.