Microsoft
70-178 · Question #24
You use Project Professional 2010 to manage a project. John, a team member, is over-allocated. You need to identify the dates on which the over-allocation occurs. What should you do?
The correct answer is B. Use the Team Planner view. See the full explanation below for the reasoning.
Question
You use Project Professional 2010 to manage a project. John, a team member, is over-allocated. You need to identify the dates on which the over-allocation occurs. What should you do?
Options
- AUse the default Leveling Gantt view.
- BUse the Team Planner view.
- CUse the Timeline view.
- DUse the Task Information dialog box.
- EUse the Task Details Form.
How the community answered
(41 responses)- A12% (5)
- B76% (31)
- C7% (3)
- D2% (1)
- E2% (1)
Community Discussion
No community discussion yet for this question.