Question

You use Project Professional 2010 to manage a project. John, a team member, is over-allocated. You need to identify the dates on which the over-allocation occurs. What should you do?

Options

  • AUse the default Leveling Gantt view.
  • BUse the Team Planner view.
  • CUse the Timeline view.
  • DUse the Task Information dialog box.
  • EUse the Task Details Form.