You need to create a new project schedule by using tasks from an existing project. You need to achieve this goal without inheriting actual hours from the existing project. What would you do first?

The correct answer is C. Open the previously saved project schedule and save it as a template. When you save a project as a template, you can remove baseline data, actuals, resource pay rates, fixed cost information, and task publishing status.

Managing Enterprise Project Management (EPM) Components

Question

You need to create a new project schedule by using tasks from an existing project. You need to achieve this goal without inheriting actual hours from the existing project. What would you do first?

Options

  • AOn the File menu in Project 2010, use one of the existing templates.
  • BSave the task list in Microsoft Excel and use the Project Import Wizard.
  • COpen the previously saved project schedule and save it as a template.
  • DSave the task list as a Microsoft Excel template.

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    84% (27)
  • D
    3% (1)

Explanation

When you save a project as a template, you can remove baseline data, actuals, resource pay rates, fixed cost information, and task publishing status.