You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure…
The correct answer is A. - Highlight the new summary task. See the full explanation below for the reasoning.
Question
You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure that Baselinez displays work hours in the new summary task. What should you do?
Options
- A
- Highlight the new summary task.
- B
- Highlight the new detailed tasks.
- C
- Highlight the new summary task.
- D
- Highlight the new detailed tasks.
How the community answered
(16 responses)- A75% (12)
- B6% (1)
- C13% (2)
- D6% (1)