Microsoft
70-178 · Question #42
70-178 Question #42: Real Exam Question with Answer & Explanation
The correct answer is D. Apply the Critical Tasks filter.. See the full explanation below for the reasoning.
Question
You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?
Options
- AApply the Priority group.
- BApply the Incomplete Tasks filter.
- CApply the Late Tasks filter.
- DApply the Critical Tasks filter.
- EApply the Status group.
Community Discussion