70-178 Question #42: Real Exam Question with Answer & Explanation

The correct answer is D. Apply the Critical Tasks filter.. See the full explanation below for the reasoning.

Question

You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?

Options

  • AApply the Priority group.
  • BApply the Incomplete Tasks filter.
  • CApply the Late Tasks filter.
  • DApply the Critical Tasks filter.
  • EApply the Status group.