Microsoft
70-178 · Question #42
You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?
The correct answer is D. Apply the Critical Tasks filter. See the full explanation below for the reasoning.
Question
You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?
Options
- AApply the Priority group.
- BApply the Incomplete Tasks filter.
- CApply the Late Tasks filter.
- DApply the Critical Tasks filter.
- EApply the Status group.
How the community answered
(21 responses)- A10% (2)
- C5% (1)
- D86% (18)
Community Discussion
No community discussion yet for this question.