All tasks in your project use the Auto Schedule mode. Several tasks are in progress. You need to reschedule all the remaining work on the project. You also need to achieve this goal without having…

The correct answer is A. Click Update Project. See the full explanation below for the reasoning.

Question

All tasks in your project use the Auto Schedule mode. Several tasks are in progress. You need to reschedule all the remaining work on the project. You also need to achieve this goal without having rigid constraints set to your project's tasks. What should you do?

Options

  • AClick Update Project.
  • BClick Calculate Project.
  • CChange the Status Date field.
  • DClick Move Project.

How the community answered

(20 responses)
  • A
    80% (16)
  • B
    5% (1)
  • C
    5% (1)
  • D
    10% (2)