You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not…
The correct answer is C. Set the constraint type to Start No Earlier Than. See the full explanation below for the reasoning.
Question
You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not change automatically. How should you configure Task 2?
Options
- ASet the task type to Fixed Duration.
- BSet the lag to two elapsed days (2ed).
- CSet the constraint type to Start No Earlier Than.
- DSet the schedule mode to Manually Scheduled.
How the community answered
(34 responses)- A9% (3)
- B3% (1)
- C85% (29)
- D3% (1)