You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not change automatically. How should you configure Task 2?
Options
- ASet the task type to Fixed Duration.
- BSet the lag to two elapsed days (2ed).
- CSet the constraint type to Start No Earlier Than.
- DSet the schedule mode to Manually Scheduled.